Engineering Conditions for Temporary Land Allocations
for works site and works area
for the Development of Lok Ma Chau Loop
Land Decontamination and Advance Engineering Works (PWP Item No. 7748CL)
Use
(1)
(a)
The area coloured pink and pink hatched black on the
attached plan (hereinafter referred to as "the site") shall not
be used for any purpose other than for works site and works
area for the Development of Lok Ma Chau Loop - Land
Decontamination and Advance Engineering Works (PWP
Item No. 7748CL).
(b)
In the event that any change in the use or development of
the site is proposed the allocatee after having obtained the
approval of the Planning Department shall apply for
approval to the District Lands Officer/ Yuen Long
(hereinafter referred to as "the District Lands Officer") who
may, if approval is granted, impose additional conditions or
direct that a new allocation is necessary.
(c)
Excavation within the site in connection with the aforesaid
purpose is permitted.
Term
(2)
The site is hereby allocated for the period from 22 June 2018 to 30
June 2022 and thereafter half-yearly. In the event that the allocation to be
terminated, a 6 months'notice shall be given to the allocatee to hand back the
site.
Formation
(3)
No site formation or general disturbance of existing site conditions
shall be undertaken without the prior approval in writing of the appropriate
authority which in granting consent may impose such conditions as it sees fit.
Setting out
(4)
(a)
Upon application by the allocatee, the Senior Land
Surveyor/ Yuen Long (hereinafter referred to as "the Senior
Land Surveyor") shall, if he considers it necessary, cause
the boundaries of the site to be set out on the ground.
(b)
The allocatee or his authorized representative after such
setting out shall attend at the site to take over the boundary
marks. The allocatee shall take or cause to be taken all
proper care and precautions to safeguard the boundary
marks from any disturbance whatsoever.
(c)
The Senior Land Surveyor shall only provide the initial
setting out. Any replacement of missing or disturbed
boundary marks that may become necessary, shall be the
responsibility of the allocatee, either by charge to his
contractor or by other arrangements with private surveyors.
Cessation of User
(5)
(a)
In the event that the site or any part thereof has ceased to be
used for the purposes specified in Condition No. (1), the
District Lands Officer shall have full power to terminate
this allocation and retake possession of the whole or any
part of the site upon 6 calendar months'notice in writing
- 7 -
Erection of
(37)
The allocatee shall, within 3 months from the date on which the
signboard
site is taken over by him, erect and maintain within the site in a position as shall
be detem血ed by the District Lands Officer as being close to the ingress point to
the site for the passage of motor vehicles referred to in Condition No. (15)(a)
hereof a sign clearly showing the name of the allocatee, the use of the site or the
nature of the project to be carried out on the site together with the telephone
number and the facsimile number of the officer to whom members of the public
may contact should they wish to lodge any complaints or make any enquiries
relating to the site.
Decontamination
(38)
The allocatee shall, in connection with the occupation and use of
the site, ensure that the site is free from contamination. In the event that the site
is found to be contaminated by any substance, such as soil or groundwater
contaminant, the allocatee shall remove all contaminate substance from the site
and its adjoining area, if necessary, and reinstate the site to the satisfaction of and
prior to the handing back of the site to the District Lands Officer at the expiry of
the allocation. The cost of such decontamination work shall be paid for as part
of the project.
/
':
,
LOCATION
', /
COLOURED PINK ANO PINK HATCHED BLACK AREA 916 000 SOUARE METERS )ABOUT)
FIio No. DLOYLB/YGS/2018, DSO/YL/W/125/2018
FOR IDENTIFICATION PURPOSES ONLY
2-NE-23A, 238, 23C, 23D,
TEMPORARY GOVERNMENT LAND ALLOCATION No TYlJO"
S"'"Y Shoot No. 2-SE-JA & 38
凪逋農悶靠這1i'm置
f'ce, Yuen Long
WORKS SITE AND WORKS AREA FOR THE DEVELOPMENT OF
O.Z.P. No.······
i
'""'"'"""'"""''""'。,,,..... , .. ,
LOK MA CHAU LOOP - LAND DECONTAM!NATIDN AND ADVANCE ENGINEERING WORKS
CIVIL ENGINEERING AND DEVELOPMENT DEPARTMENT
Rof"'°"'" Plaa No. --
PLAN No. YLM10170a